We have reached a large milestone — the crane is coming down and the completed units for mock walks are up! These completed townhouse units will be used to pass owner inspections.

The West Building exterior wrap is still being applied and the interior framing is complete. Drywall has been applied to about half of the west building. Permanent power has been delayed but should be at the east building within the month.

In the next few weeks, we will reach another large milestone with the east side building being completed as we focus on power for the building with the appliances and flooring installations following.