A Video Progress Update

We’re making great progress on the buildings this week! In the east building, we’re pouring slabs on grade, the framers have started framing and we”’ be celebrating the masonry tower topout later this month. In the West building, we’re working on the underground parking columns, building footings and walls, installing underground plumbing and putting in the building’s electrical system. In a few week’s, we’ll be pouring underground parking floors this month.

Watch the video below to take a peek inside the fences of our jobsite and see the progress for yourself!